Voght Dog Park Project

^

Canford Ave Rebuild

Construction Start: November 2021
Construction End: February 2023

View project details >

^

C-EPA Claybanks

Engineering Start: November 2023
Construction Start:
July 2025
Construction End: December 2025

View project details >

^

C-EPA North (Public Works) Dike

Engineering Start: September 2023
Construction Start:
May 2024
Construction End: November 2024

View project details >

^

Rapid Infiltration Basins

Construction Start: January 2022
Construction End: September 2022

View project details >

^

Water line Directional Drilling

Construction Start: April 2022
Construction End: January 2024

View project details >

^

Dog park

Construction Start: June 2022
Construction End: November 2022

View project details >

^

Green Space Restoration

Construction Start: July 2022
Construction End: May 2023

View project details >

^

Road/Sidewalk Repair

Construction Start: July 2022
Construction End: October 2023

View project details >

^

Main St Bridge Riprap

Construction Start: May 2023
Construction End: December 2023

View project details >

^

Middlesboro bridge

Engineering Start: January 2022
Construction Start:
March 2024
Construction End: November 2024

View project details >

^

Voght Park and Track

Construction Start: May 2023
Construction End: August 2024

View project details >

^

Civic building and property repair

Construction Start: November 2021
Construction End: December 2024

View project details >

Overview

The City of Merritt has finalized construction of a new fully-funded, 2000-square metre dog park area, on a small section of the North-West corner of Voght Park.

The new dog park includes separate run areas for large and small dogs, surrounded with black chain-link fencing and secure gated entrances. The Dog Park includes a dog water drinking fountain, picnic tables, and will soon include tree plantings inside and outside the dog park area.

Relocated the dog park from the location beside public works to the field East of Centennial Park. BC Government deemed that location not acceptable, so moved again to the final spot in Voght Park.

Fencing, trees, grass, and signage.

Funding

Please note that with the opening of the Voght Dog Park, the temporary dog park in Collettville has now closed, as the City does not have permission to continue that type of usage in that area.

The City will continue to apply for funding for different parks and recreational opportunities, including dog parks located in other areas of town.

Status

Complete

Project Cost

$110,000

Notes

Project start: June 2022
Project end: November 2022