Water line Directional Drilling

^

Canford Ave Rebuild

Construction Start: November 2021
Construction End: February 2023

View project details >

^

C-EPA Claybanks

Engineering Start: November 2023
Construction Start:
July 2025
Construction End: December 2025

View project details >

^

C-EPA North (Public Works) Dike

Engineering Start: September 2023
Construction Start:
May 2024
Construction End: November 2024

View project details >

^

Rapid Infiltration Basins

Construction Start: January 2022
Construction End: September 2022

View project details >

^

Water line Directional Drilling

Construction Start: April 2022
Construction End: January 2024

View project details >

^

Dog park

Construction Start: June 2022
Construction End: November 2022

View project details >

^

Green Space Restoration

Construction Start: July 2022
Construction End: May 2023

View project details >

^

Road/Sidewalk Repair

Construction Start: July 2022
Construction End: October 2023

View project details >

^

Main St Bridge Riprap

Construction Start: May 2023
Construction End: December 2023

View project details >

^

Middlesboro bridge

Engineering Start: January 2022
Construction Start:
March 2024
Construction End: November 2024

View project details >

^

Voght Park and Track

Construction Start: May 2023
Construction End: August 2024

View project details >

^

Civic building and property repair

Construction Start: November 2021
Construction End: December 2024

View project details >

Overview

Replaced the destroyed water main crossing the coldwater river.

New line is buried deeper and lies along a better alignment.

Project Cost

$640,000

Status

Complete

Notes

Project start: April 2022
Project end: January 2024