Rapid Infiltration Flood Repairs

^

Canford Ave Rebuild

Construction Start: November 2021
Construction End: February 2023

View project details >

^

C-EPA Claybanks

Engineering Start: November 2023
Construction Start:
July 2025
Construction End: December 2025

View project details >

^

C-EPA North (Public Works) Dike

Engineering Start: September 2023
Construction Start:
May 2024
Construction End: November 2024

View project details >

^

Rapid Infiltration Basins

Construction Start: January 2022
Construction End: September 2022

View project details >

^

Water line Directional Drilling

Construction Start: April 2022
Construction End: January 2024

View project details >

^

Dog park

Construction Start: June 2022
Construction End: November 2022

View project details >

^

Green Space Restoration

Construction Start: July 2022
Construction End: May 2023

View project details >

^

Road/Sidewalk Repair

Construction Start: July 2022
Construction End: October 2023

View project details >

^

Main St Bridge Riprap

Construction Start: May 2023
Construction End: December 2023

View project details >

^

Middlesboro bridge

Engineering Start: January 2022
Construction Start:
March 2024
Construction End: November 2024

View project details >

^

Voght Park and Track

Construction Start: May 2023
Construction End: August 2024

View project details >

^

Civic building and property repair

Construction Start: November 2021
Construction End: December 2024

View project details >

Overview

The Rapid Infiltration Basins project removed flood debris and sediment from City of Merritt Wastewater Treatment Plant areas, including the Rapid Infiltration Basins. Install a new liner in the primary basin to replace the old destroyed liner.

During the 2021 Atmosphere River Event, the Rapid Infiltration Basins were inundated and filled with debris and sediment. The RI Basins are an integral part of the current wastewater treatment plant, and are used as part of the water disposal process.

This sediment needed to be removed from the RI Basins, a new liner needed to be installed, and a secondary clay liner needed to be finished as well.

Funding

Insurance funded.

Status

Complete

Project Cost

$2,995,012

Notes

Project start: January 2022
Project end: September 2022