Flood Mitigation Department Projects

^

C-EDR 129/130 Setback Dike

Engineering Start: Winter 2025
Construction Start:
Summer 2026
Construction End:
Summer 2030

Status: Current

View project details >

^

C-EDR - Rapid Infiltration Basin

Engineering Start: Dec 2025
Engineering Completed: Q1 2026
Construction Start: Planned Q3 2026
Construction End: Planned Q4 2026

Status: Current

View project details >

^

C-EPA Middlesboro Phase 1

Engineering Start: November 2023
Construction Start:
2027
Construction End:
2027

Status: Current

View project details >

^

Cottonwood Habitat Overstory Management Program

Construction Start: February 2025
Construction End: Ongoing

Status: Current

View project details >

^

Fir Bank Stabilization and Coldwater Realignment

Engineering Start: 2025
Construction Start: Spring 2026
Construction End: Fall 2026

Status: Current

View project details >

^

Hesco Baskets

Construction Start: November 2021
Construction End: Ongoing

Status: Current

View project details >

^

STUWI(x) Naturalization Project

Engineering Start: 2025
Construction Start:
Fall 2026
Construction End: Fall 2027

Status: Current

View project details >

^

Voght Street Pump Station

Engineering Start: Spring 2026
Construction Start: Summer 2027
Completion: Fall 2027

Status: Current

View project details >

^

Canford Pump Station

Status: Unfunded

View project details >

^

C-EPA Middlesboro Phase 2

Status: Unfunded

View project details >

^

C-EPA Middlesboro Phase 3

Status: Unfunded

View project details >

^

Houston Godey

Status: Unfunded

View project details >

^

Main Street Bridge Improvements

Status: Unfunded

View project details >

^

Canford Ave Rebuild

Construction​ Start: November 2021
Construction End: February 2023

Status: Complete

View project details >

^

C-EPA North (Public Works) Dike

Engineering Start: September 2023
Construction Start:
May 2024
Construction End: November 2024

Status: Complete

View project details >

^

C-EPA Claybanks

Engineering Start: November 2023
Construction Start:
July 2025
Construction End: December 2025

Status: Complete

View project details >

^

Civic building and property repair

Construction Start: November 2021
Construction End: December 2024

Status: Complete

View project details >

^

Dog park

Construction Start: June 2022
Construction End: November 2022

Status: Complete

View project details >

^

Green Space Restoration

Construction Start: July 2022
Construction End: May 2023

Status: Complete

View project details >

^

Main St Bridge Riprap

Construction Start: May 2023
Construction End: December 2023

Status: Complete

View project details >

^

Middlesboro bridge

Construction Start: January 2022
Construction End: November 2024

Status: Complete

View project details >

^

Rapid Infiltration Flood Repairs

Construction Start: January 2022
Construction End: September 2022

Status: Complete

View project details >

^

Road/Sidewalk Repair

Construction Start: July 2022
Construction End: October 2023

Status: Complete

View project details >

^

Voght Park and Track

Construction Start: May 2023
Construction End: August 2024

Status: Complete

View project details >

^

Water line Directional Drilling

Construction Start: April 2022
Construction End: January 2024

Status: Complete

View project details >

Planned Construction 2027-2029

Version 2 | August 21, 2026

2027

2028

2029

2

3

4

9

10

11

12

6

7

8

1

5

13

Pine Street Dike

Hill Street Dike

Walnut Ave Dike

Central School Dike

Voght St Pump Station

Middlesboro Phase 1

STUWI(x) Naturalization

Voght Park Dike

Spring Island Dike

Chapman Dike

RI Basin Dike

Main Street Dike

Pine Street
Temporary Dike Removal

The preliminary schedule is based on modelling nine ways to build the dikes while limiting the chance that construction shifts flood risk onto nearby homes.

The modelling favours building connected sections because gaps in a partly built dike can let water into residential areas and obstruct its return to the river. It also favours building parts of Dike 129 first: building Dike 130 first could increase flooding near homes south of Dike 129. Segment 1 is left until the final year because building it early could raise water levels around Hicks Avenue, while other segments provide earlier protection for residential properties.

The recommended sequence is Middlesboro Phase 1 and Segments 2, 3, 4 and 9 in 2027; Segments 6, 7 and 8 in 2028; and Segments 1 and 5 in 2029, with Segment 9 timed ahead of the planned Voght Street Pump Station work.

This remains a preliminary, but likely recommendation, with contractor availability, contracting strategy and effects on other dikes to be assessed during detailed design.