Join Us!

Open House

Date: Thursday, May 21, 2026
Time: 4:00 PM – 8:00 PM

Learn More Here >

Community Site Walk

Date: Friday, May 22, 2026
Time: 10:00 AM – 1:00 PM

Learn More Here >

Flood Mitigation Department Projects

^

C-EDR 129/130 Setback Dike

Engineering start: Winter 2025
Project start:
Summer 2026
Project end:
Summer 2030

Status: current

View project details >

^

C-EDR - Rapid Infiltration Basin

Engineering Start: Dec 2025
Engineering Completed: Q1 2026
Project start: Planned Q3 2026
Project end: Planned Q4 2026

Status: current

View project details >

^

C-EPA Middlesboro Phase 1

Engineering start: November 2023
Construction Start:
2026 or 2027, permitting dependant
Construction End:
2027

Status: current

View project details >

^

Cottonwood Habitat Overstory Management Program

Project start: February 2025
Project end: ongoing

Status: current

View project details >

^

Fir Bank Stabilization and Coldwater Realignment

Engineering start: 2025
Construction start: Spring 2026
Construction end: Fall 2026

Status: current

View project details >

^

Hesco Baskets

Project start: November 2021
Ongoing ongoing until funds are secured and dikes constructed or removed.

Status: current

View project details >

^

Main Street Bridge Improvements

Project start: TBA
Project end: TBA

Status: current

View project details >

^

STUWI(x) Naturalization Project

Engineering start: Community led, evolving
Construction start:
October 2025
Construction end: 2027

Status: current

View project details >

^

Voght Street Pump Station

Engineering Start: Fall 2026
Construction Start Date: Summer 2027 (pending approvals and permitting)
Completion: TBA

Status: current

View project details >

^

Canford Pump Station

Status: Unfunded

View project details >

^

C-EPA Middlesboro Phase 2

Status: Unfunded

View project details >

^

C-EPA Middlesboro Phase 3

Status: Unfunded

View project details >

^

Houston Godey

Status: Unfunded

View project details >

^

Canford Ave Rebuild

Project start: November 2021
Project end: February 2023

Status: complete

View project details >

^

C-EPA North (Public Works) Dike

Engineering start: September 2023
Construction start:
May 2024
Construction end: November 2024

Status: complete

View project details >

^

C-EPA Claybanks

Engineering start: November 2023
Construction start:
July 2025
Construction end: December 2025

Status: complete

View project details >

^

Civic building and property repair

Project start: November 2021
Project end: December 2024

Status: complete

View project details >

^

Dog park

Project start: June 2022
Project end: November 2022

Status: complete

View project details >

^

Green Space Restoration

Project start: July 2022
Project end: May 2023

Status: complete

View project details >

^

Main St Bridge Riprap

Project start: May 2023
Project end: December 2023

Status: complete

View project details >

^

Middlesboro bridge

Project start: January 2022
Project end: November 2024

Status: complete

View project details >

^

Rapid Infiltration Flood Repairs

Project start: January 2022
Project end: September 2022

Status: complete

View project details >

^

Road/Sidewalk Repair

Project start: July 2022
Project end: October 2023

Status: complete

View project details >

^

Voght Park and Track

Project start: May 2023
Project end: August 2024

Status: complete

View project details >

^

Water line Directional Drilling

Project start: April 2022
Project end: January 2024

Status: complete

View project details >

Flood Mitigation Department

The Merritt Flood Mitigation Department is focused on protecting the community from future flood risks through a comprehensive Flood Mitigation Plan.

This plan includes the development of a dike system and other infrastructure projects to safeguard key areas.

The department emphasizes strategic planning, Indigenous Engagement, project partner collaboration, and community involvement to build resilience against climate-related disasters.

By leveraging insights from other municipalities and experts, the department employs a phased, milestone-driven approach to implement effective flood protection measures.

The goal is to create sustainable solutions that enhance Merritt’s preparedness and response capabilities, ensuring long-term safety and stability for the community.

A resilient tulip, growing out of the mud after the 2021 flood in Merritt, BC

Photo Credit: Kevin Vilac Chief Operator of the Water and Wastewater Systems. May 10, 2022

“Today while doing our rounds this Tulip appeared from nowhere. Amidst the chaos and destruction here is this beautiful flower, like the residents of Merritt. If it can do it, so can we! I hope this Tulip helps anyone that may need a boost to push forward and just be you!”

Council Update | Q1 – 2026

In large civil construction projects, Q1 is a busy time for engineering and project management staff, and this was the theme for 2026-Q1.

Following the execution of the complex and technical RFP process for the engineer in 2025- Q4 and the selection of Stantec as the Engineer-of-Record, the detailed dike engineering work began in earnest in January.

This conceptual dike alignment was drafted in 2021 for the Flood Mitigation Plan, so now the engineering team is doing the first work on that plan since the 2021 project.

Going into 2026-Q2, any proposed realignments or changes to this plan will come to council for input and approval, and detailed engineering for the 9 segments of dike construction will be finalized during 2026-Q3 and Q4.

Also during 2026-Q1, the Land Acquisition team reached the critical milestone of property offers going out, and also has multiple accepted offers. This work will continue at speed during the remainder of 2026.

These are exciting times for resiliency in the City of Merritt, many in BC are looking at the works being done in this City for inspiration and direction.

Sean Strang,
Director of Recovery and Mitigation

Merritt Flood Mitigation Quarterly Report | Council Update Q1 2026

2026 Quarterly Reports

2025 Quarterly Reports

Merritt flood mitigation map
STUWI(x) Naturalization Project C-EDR 129 Setback Dike C-EDR 130 Setback Dike C-EPA North (Public Works) Dike Main St Bridge Improvements Fir Bank Stabilization and Coldwater Realignment Middlesboro bridge C-EPA Claybanks Dike C-EPA Middlesboro Phase 1 C-EPA Middlesboro Phase 2 C-EPA Middlesboro Phase 3 Houston Godey Voght Street Pump Station Canford Pump Station

STUWI(x) Naturalization Project

STUWI(x) Naturalization Project | Merritt Flood Mitigation

Engineering start: Community led, evolving
Construction start:
October 2025
Construction end: 2027

Status: current

View project details >

C-EDR 129 Setback Dike

Merritt Flood Mitigation Department | Coldwater - Expanded Dike Rebuild - Rapid Infiltration Basin | February 2026

Engineering start: Winter 2025
Project start:
Summer 2026
Project end:
Summer 2030

Status: current

View project details >

C-EDR 130 Setback Dike

Merritt Flood Mitigation Department | Coldwater - Expanded Dike Rebuild - Rapid Infiltration Basin | February 2026

Engineering start: Winter 2025
Project start:
Summer 2026
Project end:
Summer 2030

Status: current

View project details >

C-EPA North (Public Works) Dike

C-EPA North (Public Works) Dike

Engineering start: September 2023
Construction start:
May 2024
Construction end: November 2024

Status: complete

View project details >

Main St Bridge Improvements

Merritt BC, Main st. bridge

Project start: May 2023
Project end: December 2023

Status: complete

View project details >

Fir Bank Stabilization and Coldwater Realignment

Fir Ave Bank Stabilization and Coldwater Realignment Projects | Merritt Flood Mitigation Department

Engineering start: 2025
Construction start: Spring 2026
Construction end: Fall 2026

Status: current

View project details >

Middlesboro bridge

Middlesboro bridge progress

Project start: January 2022
Project end: November 2024

Status: complete

View project details >

C-EPA Claybanks Dike

Drone Photos September 2025 | C-EPA Claybanks Dike Project

Engineering start: November 2023
Construction start:
July 2025
Construction end: December 2025

Status: complete

View project details >

C-EPA Middlesboro Phase 1

Merritt Flood Mitigation Department C-LAP Dike 129/130 Mapping

Engineering start: November 2023
Construction Start:
2026 or 2027, permitting dependant
Construction End:
2027

Status: current

View project details >

C-EPA Middlesboro Phase 2

Unfunded project

Status: Unfunded
Dike length: 135m

View project details >

C-EPA Middlesboro Phase 3

Unfunded project

Status: Unfunded
Dike length: 550m

View project details >

Houston Godey

Unfunded project

Status: Unfunded
Dike length: 740m

View project details >

Voght Street Pump Station

potential inundation zone of the Coldwater River

Engineering Start: Fall 2026
Construction Start Date: Summer 2027 (pending approvals and permitting)
Completion: TBA

Status: current

View project details >

Canford Pump Station

Unfunded project

Status: Unfunded

View project details >