Flood Mitigation Department Projects

^

C-EDR 129/130 Setback Dike

Engineering start: Winter 2025
Project start:
Summer 2026
Project end:
Summer 2030

Status: current

View project details >

^

C-EPA Middlesboro Phase 1

Engineering start: November 2023
Construction start:
2026
Construction end: 2027

Status: current

View project details >

^

Cottonwood Habitat Overstory Management Program

Project start: February 2025
Project end: ongoing

Status: current

View project details >

^

Fir Ave Bank Stabilization and Coldwater Realignment Projects

Engineering start: 2026
Construction end: 2026

Status: current

View project details >

^

Hesco Baskets

Project start: November 2021
Will be in place until Dikes constructed or removed.

Status: current

View project details >

^

Main Street Bridge Improvements

Project start: TBA
Project end: TBA

Status: current

View project details >

^

STUWI(x) Naturalization Project

Engineering start: 2026
Construction start:
2026
Construction end: 2027

Status: current

View project details >

^

Voght Street Pump Station

Engineering Start: Fall 2026
Construction Start Date: Summer 2027 (pending approvals and permitting)
Completion: TBA

Status: current

View project details >

^

Canford Pump Station

Status: Unfunded

View project details >

^

C-EPA Middlesboro Phase 2

Status: Unfunded

View project details >

^

C-EPA Middlesboro Phase 3

Status: Unfunded

View project details >

^

Houston Godey

Status: Unfunded

View project details >

^

Canford Ave Rebuild

Project start: November 2021
Project end: February 2023

Status: complete

View project details >

^

C-EPA North (Public Works) Dike

Engineering start: September 2023
Construction start:
May 2024
Construction end: November 2024

Status: complete

View project details >

^

C-EPA Claybanks

Engineering start: November 2023
Construction start:
July 2025
Construction end: December 2025

View project details >

^

Civic building and property repair

Project start: November 2021
Project end: December 2024

Status: complete

View project details >

^

Dog park

Project start: June 2022
Project end: November 2022

Status: complete

View project details >

^

Green Space Restoration

Project start: July 2022
Project end: May 2023

Status: complete

View project details >

^

Main St Bridge Riprap

Project start: May 2023
Project end: December 2023

Status: complete

View project details >

^

Middlesboro bridge

Project start: January 2022
Project end: November 2024

Status: complete

View project details >

^

Rapid Infiltration Flood Repairs

Project start: January 2022
Project end: September 2022

Status: complete

View project details >

^

Road/Sidewalk Repair

Project start: July 2022
Project end: October 2023

Status: complete

View project details >

^

Voght Park and Track

Project start: May 2023
Project end: August 2024

Status: complete

View project details >

^

Water line Directional Drilling

Project start: April 2022
Project end: January 2024

Status: complete

View project details >

Flood Mitigation Department

The Merritt Flood Mitigation Department is focused on protecting the community from future flood risks through a comprehensive Flood Mitigation Plan.

This plan includes the development of a dike system and other infrastructure projects to safeguard key areas.

The department emphasizes strategic planning, Indigenous Engagement, project partner collaboration, and community involvement to build resilience against climate-related disasters.

By leveraging insights from other municipalities and experts, the department employs a phased, milestone-driven approach to implement effective flood protection measures.

The goal is to create sustainable solutions that enhance Merritt’s preparedness and response capabilities, ensuring long-term safety and stability for the community.

A resilient tulip, growing out of the mud after the 2021 flood in Merritt, BC

Photo Credit: Kevin Vilac Chief Operator of the Water and Wastewater Systems. May 10, 2022

“Today while doing our rounds this Tulip appeared from nowhere. Amidst the chaos and destruction here is this beautiful flower, like the residents of Merritt. If it can do it, so can we! I hope this Tulip helps anyone that may need a boost to push forward and just be you!”

Council Update | Q3 – 2025

Summer and fall are peak construction seasons, particularly for riverside work.

The Coldwater River has one of the shortest “work windows” in BC, just 11 days (July 22–Aug 1). Work outside this window requires costly environmental measures such as fish salvage, water isolation, and sediment control.

Within this narrow period, two key 2025 projects were completed: the Claybanks RV Park Dike and Dike 130 debris removal at the Stuwi(x) site. The rest of the project work was able to occur outside this window, as it was further back from the river.

Provincial staffing changes over summer slowed claim processing and grant approvals. The Dike 129/130 project, announced in March, did not receive provincial approval to proceed. Despite efforts from staff, the CAO, and the Mayor, funding was not approved in the quarter, delaying engineering procurement.

The team advanced procurement preparation and land acquisition work, and launched a minidocuseries showcasing Merritt’s flood mitigation progress, with filming scheduled for Q4.

Overall, the summer delivered strong results in construction and planning.

The department continues to build a reputation for effective execution and strategic preparation.

Sean Strang,
Director of Recovery and Mitigation

Rapid Infiltration Basins

Construction end: September 2022

Status: complete

C-EDR 129 Setback Dike

Construction: 2027-2029
Dike Length: 2.9 KM

Status: current

Main St Bridge Riprap Project

Project start: May 2023
Project end: December 2023

Status: complete

Main Street Bridge Improvements

Status: unfunded

Middlesboro Bridge Rebuild

Construction end: November 2024

Status: complete

C-EPA North (Public Works) Dike

Construction end: November 2024

Status: complete
Dike Length: 280 m

STUWI(x) Naturalization Project

Engineering start: Community led, evolving
Construction start:
October 2025
Construction end: 2027

Status: current

Canford Pump Station

Status: unfunded

C-EPA Middlesboro Phase 2

Status: unfunded

C-EPA Middlesboro Phase 3

Status: unfunded

Voght Street Pump Station

Location: TBA

Status: current

Fir Ave Bank Stabilization and Coldwater Realignment

Construction start: 2026

Status: current
Dike length: 120m

C-EPA Claybanks Dike

Construction end: December 2025

Status: complete
Dike length: 190m

C-EPA Middlesboro Phase 1

Construction start: TBA

Status: current
Dike length: 90m

Houston Godey

Status: unfunded

Hesco Baskets

Status: current ongoing maintenance

Completed

20%

In Progress

50%

Unfunded

30%