Overview
The November 2021 atmospheric river caused widespread flooding in Merritt and breached a section of Dike 129 east of Pine Street.
As part of the emergency response, a temporary dike was built to reduce the risk of the Coldwater River continuing to flow along a new path carved by the flood.
The project will remove approximately 150 metres of temporary dike and regrade the area to reconnect the Coldwater River with its floodplain. The site is east of Pine Street, upstream of where the Coldwater River meets the Nicola River.
Construction is expected to take place in 2029, following the Dike 129 Rebuild Project. The work is expected to take approximately four weeks.
Status
Current
Notes
Engineering: Completed
Construction Start: Fall 2029
Construction End: 2029